GNFC captive plant supplies steam, while grid power costs less
Key highlights
- GNFC said its captive coal-based plant began generating steam on July 25.
- GNFC said grid electricity is currently cheaper than captive power because coal prices are high.
- GNFC plans a guaranteed test run during the current quarter before full-scale operation.
- GNFC reported Q2 production of close to 1,78,000 for ammonia and 8,700 for TDI.
powered by IRIS

GNFC said its captive coal-based plant has supplied steam since July 25, but grid electricity remained cheaper than captive generation at prevailing coal prices during its Q2 FY27 call. Management said the plant began catering to power requirements around August, while a guaranteed test run was planned during the current quarter.
Know Gujarat Narmada Valley Fertilizers & Chemicals inside out
Results, valuation, peers and who's buying, in one view.
When did GNFC’s captive coal plant begin operating?
GNFC said the captive coal-based plant began generating steam on July 25 and started catering to power requirements around August. The staged start means the plant was contributing to steam requirements during Q2 FY27, although its electricity output was not being used as GNFC’s main power source.
Management said the steam benefit was already being availed from the plant. It added that steam could be supplied at the full rate except for certain interruptions, indicating that the steam side of the facility was operating ahead of the broader full-scale operating milestone.
Why is GNFC using grid power after commissioning the captive plant?
GNFC is using grid electricity as its main power source because management said grid power is currently cheaper than captive generation at high coal prices. The company said it normally keeps the captive power plant as a fallback while using the grid as the principal power source in the current cost environment.
The plant is therefore delivering two utilities with different current economics. GNFC is taking the steam benefit from the coal-based facility, while choosing grid supply for electricity. Management linked that split directly to relative coal and grid-power costs, rather than to an inability of the captive plant to generate power.
What must happen before GNFC runs the plant at full scale?
GNFC said a guaranteed test run would take place during the current quarter, after which the captive coal-based plant would go to full scale. Management did not disclose a test date, generation capacity, capital cost or quantified saving from the facility.
The test run is the disclosed operational checkpoint for broader deployment of the plant. Until then, GNFC’s position is limited to steam being available at the full rate except for certain interruptions, while the choice between captive and grid electricity remains dependent on relative coal and power prices.
Got a follow-up? Ask IRIS
How do coal and oil prices affect GNFC’s operating costs?
GNFC said oil prices overall were lower in Q2 than in Q1, although month-to-month oil prices remained volatile and were largely linked to crude indices. Management said geopolitical developments were causing price increases and decreases within a range during the quarter.
Coal prices are the more immediate disclosed factor in the captive-power decision because management said high coal prices made grid electricity cheaper. GNFC also said it pursues cost optimisation through initiatives including sourcing and gas sourcing, but it did not identify a specific second-half FY27 programme or provide a savings target.
What does the captive plant mean for GNFC’s Bharuch and Dahej operations?
GNFC said it had no plan to shut the Bharuch plant and that Bharuch had been cost competitive compared with Dahej. Management added that operation of the captive power plant was bringing the cost positions of the two sites nearer, without providing site-level cash-cost figures.
Management said coal and gas-price dynamics can change the relative outcome between Bharuch and Dahej. It noted that TDI production at Dahej could at times be more attractive on cost than production at the first Bharuch plant, making the captive facility one factor in site economics rather than a permanent advantage for either location.
Did production disruptions affect GNFC’s Q2 chemical operations?
GNFC said both plants were operating at the time of the call, but TDI, acetic acid and ethyl acetate operations had not produced for 30 to 35 days in July because they were in a cash-loss situation. Management said this viability issue contributed to lower volumes in Q2.
For Q2, GNFC reported ammonia production of close to 1,78,000, TGU production of 44,900, AN Melt production of close to 41,000, WNA production of 1,14,000, CNA production of 41,000 and TDI production of 8,700. Management acknowledged that TDI output was lower quarter on quarter, while saying the affected product plants were subsequently operating normally.
Conclusion
GNFC’s operating update shows that the captive coal-based facility has so far changed its steam supply rather than replaced grid electricity. The July 25 steam start provides an immediate utility benefit, but high coal prices meant that the company retained grid supply for power even after the plant began catering to power requirements around August.
The next disclosed event is the guaranteed test run during the current quarter, after which management said the plant would operate at full scale. Coal and gas-price movements remain the main items to watch because GNFC said they can affect both the grid-versus-captive electricity decision and the relative cost position of its Bharuch and Dahej operations.