Jai Balaji Industries Ltd. completes 5.5 lakh TPA DI-pipe capacity
Key highlights
- JBIL has completed 5.5 lakh TPA of DI-pipe capacity.
- JBIL sold 41,000 tonnes of DI pipes in Q2FY27, versus 51,000 tonnes in Q4FY26.
- JBIL’s Q2FY27 DI-pipe realisation was Rs 56,587 per tonne, versus Rs 59,117 per tonne in Q2FY26.
- JBIL expects DI-pipe recovery in FY27-28 and identifies potential Ken-Betwa pipe demand in FY28.
powered by IRIS

Jai Balaji Industries Ltd. has completed 5.5 lakh tonnes per annum (TPA) of ductile iron (DI) pipe capacity, but Q2FY27 DI-pipe sales were 41,000 tonnes, below 51,000 tonnes in Q4FY26. JBIL says the available capacity can be ramped up if demand revives through water infrastructure and irrigation projects.
Know Jai Balaji Industries inside out
Results, valuation, peers and who's buying, in one view.
What DI-pipe capacity has JBIL completed?
JBIL has completed DI-pipe capacity of 5.5 lakh TPA. The company says the expansion has been successfully completed and the capacity is ready for utilisation as market conditions improve. Its Rajbandh Unit III in Burdwan, West Bengal, lists installed DI-pipe capacity of 5.5 lakh tonnes.
The DI-pipe business is part of JBIL’s value-added product portfolio alongside specialised ferro alloys. Management said DI pipes and specialised ferro alloys together currently contribute about 40% to 45% of revenue. The presentation does not give a FY27 DI-pipe utilisation target, instead stating that capacity utilisation can rise with market demand.
JBIL operates five manufacturing units across West Bengal and Chhattisgarh. Its integrated operations included 5.5 lakh tonnes of pig-iron capacity, 9.08 lakh tonnes of sinter capacity and 101.1 megawatts of power capacity as of March 2026, alongside the DI-pipe facility. The company also reported three railway sidings, including rail infrastructure for raw-material loading in Odisha and unloading at its plants.
What do JBIL’s DI-pipe volumes and realisations show?
JBIL’s DI-pipe operating data show that sales and production remained below their Q4FY26 levels in Q2FY27. DI-pipe production was 37,000 tonnes in Q2FY27, versus 48,000 tonnes in Q4FY26 and 41,000 tonnes in Q1FY27. Sales were 41,000 tonnes, compared with 51,000 tonnes in Q4FY26 and 44,000 tonnes in Q1FY27.
DI-pipe realisation was Rs 56,587 per tonne in Q2FY27, down from Rs 59,117 per tonne in Q2FY26 and Rs 57,581 per tonne in Q1FY27. Management described DI-pipe realisations as marginally lower, while reporting improved realisations in other products. Ferro-alloy realisation increased to Rs 2.03 lakh per tonne in Q2FY27 from Rs 1.34 lakh per tonne a year earlier.
JBIL’s annual DI-pipe sales rose from 2.39 lakh tonnes in FY24 to 2.57 lakh tonnes in FY25, then declined to 1.66 lakh tonnes in FY26. Its roadmap describes H2FY27 DI-pipe sales as the same as last year and expects a recovery in FY27-28. The figures indicate that the completed 5.5 lakh-TPA capacity is being held for a demand recovery rather than being matched by current sales volumes.
Got a follow-up? Ask IRIS
Which water projects does JBIL link to DI-pipe demand?
JBIL links a potential DI-pipe demand recovery to Jal Jeevan Mission 2.0, AMRUT 2.0 and major irrigation projects. Jal Jeevan Mission 2.0 has been extended to December 2028 with a total outlay of Rs 8.69 lakh crore, including Rs 3.59 lakh crore of central funding. The programme reported 15.80 crore rural households, or 81.6%, with tap connections against a target of 19.36 crore households.
The programme’s FY2026-27 expected budget release is Rs 67,670 crore, and the presentation says Rs 6,155 crore had been released to 13 states. Its stated focus includes reliable water services, source sustainability, operation and maintenance, and community ownership. JBIL identifies such water-distribution investment as a possible demand channel but does not disclose any DI-pipe order linked to the programme.
AMRUT 2.0 covers 4,378 statutory towns and has a total outlay of Rs 2.99 lakh crore, including Rs 76,760 crore of central funding. The programme targets 2.68 crore tap-water connections and 2.64 crore sewerage or septage connections. The presentation lists 3,528 approved water-supply projects worth Rs 1.20 lakh crore and 583 approved sewerage projects worth Rs 66,118 crore.
JBIL also points to irrigation schemes with later project timelines. The Ken-Betwa river-linking project is under implementation with an estimated cost of Rs 44,605 crore and a March 2030 completion target; the presentation identifies possible pipe demand from it in FY28. It also lists the Polavaram and Godavari-Krishna link as under execution, while stating that one of 30 identified national river links was under implementation as of February 2026.
How is JBIL sequencing investment and financial capacity?
JBIL says it has spent the full Rs 1,112 crore revised capital-expenditure programme, mostly through internal accruals, compared with the initial Rs 1,000 crore outlay. It spent Rs 36 crore in Q2FY27 on the balance capex and said the programme would be completed by the end of November 2026. DI-pipe expansion is already complete, while enhanced blast-furnace, sinter and specialised ferro-alloy capacities are scheduled for commissioning by Q4FY27.
JBIL reported net term debt of Rs 145 crore in H1FY27, down from Rs 169 crore in FY26 and Rs 3,408 crore in FY21. It reported a FY26 net term debt-to-equity ratio of 0.06 times. The company also said it had been sanctioned Rs 395 crore of working-capital loans and Rs 137 crore from HDFC Bank as working-capital or term loans.
The company’s near-term performance is supported by products beyond DI pipes. In Q2FY27, specialised ferro alloys contributed 28% of revenue, while adjusted earnings before interest, tax, depreciation and amortisation rose 93% year on year to Rs 135 crore. Revenue increased 22% to Rs 1,652 crore and profit after tax rose to Rs 77 crore from Rs 26 crore, with management citing volumes, realisations and operating efficiencies.
Conclusion
JBIL has installed 5.5 lakh TPA of DI-pipe capacity ahead of the recovery it expects in water and irrigation demand. Current operating data show the gap between capacity availability and market conditions: Q2FY27 sales of 41,000 tonnes were below the 51,000 tonnes in Q4FY26, while DI-pipe realisation fell to Rs 56,587 per tonne. Higher ferro-alloy realisations and a 28% revenue contribution from specialised ferro alloys supported Q2FY27 profitability while pipe demand remained soft.
The next disclosed milestones are completion of the Rs 1,112 crore capex programme by the end of November 2026 and commissioning of expanded blast-furnace, sinter and specialised ferro-alloy capacity by Q4FY27. Management’s roadmap expects DI-pipe recovery in FY27-28 and identifies Ken-Betwa as a potential FY28 pipe-demand source, while Jal Jeevan Mission 2.0 is scheduled to run through December 2028.