Chambal Fertilisers and Chemicals Limited advances urea plan
Key highlights
- CFCL has acquired additional land and completed fencing, geotechnical studies and contouring for the proposed urea plant.
- CFCL operates 34,00,000 MT of urea capacity across three plants at one location.
- Urea represented 62% of CFCL’s H1-FY27 segment revenue mix, versus 31% for complex fertilisers.
- CFCL reported H1-FY27 standalone operational revenue of Rs 12,026.5 crore and EBITDA of Rs 1,751.7 crore.
powered by IRIS

In Q2/H1-FY27, Chambal Fertilisers and Chemicals Limited advanced preparation for a proposed urea plant by acquiring land, completing site-enabling work and receiving in-principle gas-supplier approval, while its existing three urea plants have 34,00,000 metric tonnes (MT) of capacity. The project remains subject to government and board approvals.
Know Chambal Fertilisers & Chemicals inside out
Results, valuation, peers and who's buying, in one view.
What has CFCL completed for the new urea plant?
CFCL has acquired an additional land parcel and completed fencing, geotechnical studies and contouring for the proposed urea plant. The presentation lists these activities as completed pre-project work, but does not disclose the proposed plant’s capacity, capital cost, construction start date or commissioning schedule.
CFCL says preliminary layout work, design basis, project scoping and project scheduling are at advanced stages. Following its Invitation to Bid (ITB), lump-sum turnkey and engineering, procurement and construction (LSTK/EPC) bidders submitted expressions of interest, and CFCL expects technical-bid submission shortly.
CFCL also identifies infrastructure available for additional output at its existing location. A railway siding is operational for dispatching additional material, and CFCL reports adequate water storage in the riverbed, although the presentation does not state rail-dispatch capacity or water-storage volume.
Which approvals does CFCL still need for the project?
CFCL still requires environmental clearance, approval from the Department of Fertilizers and approval from its Board of Directors for the new urea project. Environmental clearance is in progress, and the presentation gives no expected date for any of the three decisions.
CFCL has in-principle approval from the gas supplier, but does not describe this as a final gas-supply agreement. The distinction matters because the proposed facility is intended to be a gas-based urea plant and remains conditional on the stated regulatory and board approvals.
CFCL has not disclosed a final investment decision, an EPC award or a production date. Technical bids are expected shortly, which places contractor selection after the expressions of interest received under the ITB process.
How would the project alter CFCL’s urea footprint?
CFCL says that, after the new urea plant, it would become India’s largest single-location urea producer and the world’s second-largest. This is a management statement about the post-project position and is conditional on approval by the Department of Fertilizers and CFCL’s board.
CFCL currently operates three urea plants and one Technical Ammonium Nitrate (TAN) plant at a single location. Its stated urea manufacturing capacity is 34,00,000 MT, it identifies itself as India’s largest private-sector urea manufacturer, and it reports about 10% urea market share.
The proposed addition would expand an already single-site manufacturing structure rather than create a separately disclosed location. CFCL says the larger configuration would provide further economies of scale, but it does not quantify any effect on unit costs, energy consumption, freight or profitability.
Got a follow-up? Ask IRIS
What policy backdrop applies to CFCL’s proposed plant?
The National Investment Policy for Urea-2026 (NIPU-2026) was notified to promote domestic investment in urea and strengthen India’s self-sufficiency, according to CFCL. The policy envisages eight to nine gas-based plants, providing the policy setting described alongside CFCL’s pre-project work.
NIPU-2026 separates fixed and variable costs and provides a return-on-equity band with a 12% floor and a 16% ceiling. It also provides for foreign-exchange-risk mitigation through conversion of fixed costs into Indian rupees four years after the policy notification date.
CFCL does not state that its proposed plant has been admitted to NIPU-2026. Its disclosure only says that the new urea project remains subject to Department of Fertilizers and board approval, alongside the environmental clearance that is still in progress.
How important is urea to CFCL’s current operations?
Urea accounted for 62% of CFCL’s H1-FY27 segment revenue mix, making it the company’s largest reported revenue segment. Complex fertilisers accounted for 31%, Crop Protection Chemicals, Speciality Nutrients and Seeds accounted for 6%, and TAN accounted for 1%.
CFCL reported standalone operational revenue of Rs 12,026.5 crore and earnings before interest, tax, depreciation and amortisation (EBITDA) of Rs 1,751.7 crore in H1-FY27. The half-year period is not directly comparable with the full-year figures below, but it shows the financial scale of operations while the urea project remains in preparation.
Across the three reported full years, operational revenue fell from Rs 17,966.4 crore in FY24 to Rs 16,646.2 crore in FY25, then rose to Rs 20,793.7 crore in FY26. EBITDA increased from Rs 2,044.2 crore in FY24 to Rs 2,484.2 crore in FY25 and Rs 2,679.2 crore in FY26.
CFCL has also added industrial chemicals capacity during FY27. Commercial production at its High Density Ammonium Nitrate plant began on 20 August 2026, while Weak Nitric Acid and Ammonium Nitrate Solution started production in Q1-FY27; the TAN manufacturing capacity is 2,40,000 MT.
Conclusion
CFCL has completed several disclosed preparatory steps for a new urea plant, including land acquisition, site-enabling activities and advanced preliminary engineering, while also establishing in-principle gas-supplier approval and receiving EPC bidder interest. The proposed project is material to CFCL’s existing 34,00,000 MT urea platform, whose segment represented 62% of H1-FY27 revenue.
The next disclosed items to watch are environmental clearance, approval by the Department of Fertilizers, CFCL board approval and technical-bid submission by LSTK/EPC bidders. CFCL has not disclosed the proposed plant’s capacity, project cost, financing, selected contractor, final gas arrangements or construction timetable.