NALCO targets FY31 Angul commissioning after refinery start
Key highlights
- NALCO targets fifth refinery-stream production in late December 2026 or early January 2027.
- About 34 to 35 of roughly 50 fifth-stream packages were complete on November 3, 2026.
- NALCO targets Angul mechanical completion by December 2030 and commissioning in Q1 FY31.
- NALCO estimates Angul smelter investment at Rs 17,000-18,000 crore.
powered by IRIS

National Aluminium Company Limited targets production from its fifth refinery stream in late December 2026 or early January 2027 and commissioning of the Angul brownfield smelter expansion in the first quarter of FY31. Management estimates the smelter investment at Rs 17,000-18,000 crore and targets mechanical completion by December 2030.
Know National Aluminium Company inside out
Results, valuation, peers and who's buying, in one view.
When will NALCO's fifth refinery stream start production?
NALCO plans integrated trials and production from its fifth refinery stream in the last week of December 2026 or early January 2027. On its November 3, 2026 Q2 FY27 earnings call, management said the project was in an advanced stage of mechanical completion, with trials and testing already under way for completed packages.
Of about 50 packages, NALCO had completed around 34 to 35 by the call date. The remaining three or four packages on the critical path were about 90% to 92% physically complete, management said. The final production date therefore depends on completing these packages and integrating them with the rest of the refinery rather than only finishing individual no-load trials.
The fifth stream is the nearer-term part of NALCO's capacity plan, whereas the Angul smelter expansion has an execution period extending to FY31. Management said the new refinery stream would add about 2 lakh tonnes of alumina in the second half of FY27 and could contribute about Rs 150 crore to profit before tax in that period.
How much alumina can NALCO produce during the refinery ramp-up?
NALCO expects the fifth stream to take about three to five months after its start to reach 100% of rated capacity. Management said the stream may produce about 0.75 million to 0.80 million tonnes in its first full year of operation, below its 1 million-tonne rated capacity because of the ramp-up period.
For FY27, NALCO indicated alumina production of about 2.45 million tonnes, compared with its earlier 2.5 million-tonne guidance. Management said the existing four streams were operating at an annualised rate of 2.3 million tonnes, while a January 2027 start would provide only a partial-year contribution from the fifth stream.
Management also linked the refinery start to its second-half FY27 margin expectations. It said the extra alumina from the new stream, improved techno-economic performance and the absence of a first-half royalty impact could together provide Rs 300 crore to Rs 350 crore of additional benefit in the second half, while noting that alumina prices and operating conditions remain relevant.
When will NALCO commission the Angul smelter expansion?
NALCO targets mechanical completion of the Angul brownfield smelter expansion by December 2030 and commissioning in the first quarter of FY31. Management said it had provided this timetable to the Ministry of Mines and was maintaining planned milestones, although it allowed for a possible delay of one to three months.
NALCO signed a technology-licence agreement with Dubai-based EGA about two months before the November 2026 call. Management expects to complete the detailed project report, or DPR, in January or February 2027 and then place it before the board, potentially in February 2027. These dates are management targets and board approval had not been obtained at the time of the call.
Following board approval, NALCO expects ordering of major packages to take six to eight months and aims to complete package ordering by December 2027. Land acquisition was described as being at an advanced stage, with management expecting land availability in February or March 2027. Groundwork is planned for January or February 2028, followed by three to three-and-a-half years of project execution.
Got a follow-up? Ask IRIS
How much will NALCO spend on Angul and its power project?
NALCO estimates the Angul brownfield smelter project will require Rs 17,000-18,000 crore of investment. Management put the combined value of major smelter and power-plant packages at about Rs 25,000 crore, indicating that the power project is a significant linked part of the expansion even though it did not disclose a standalone plant cost.
Management said capital expenditure would become material from FY29, when groundwork and major orders advance. It indicated spending of about Rs 200 crore to Rs 300 crore before the larger build-out, including the technology licence, then annual spending of about Rs 5,000 crore to Rs 6,000 crore initially and about Rs 7,000 crore to Rs 8,000 crore in later FY29 to FY31 periods. The call did not disclose project financing or a year-by-year split between smelter and power expenditure.
The required power plant is planned through a 50:50 joint venture with Neyveli Lignite Corporation. Management said the joint venture had been approved by the Department of Investment and Public Asset Management, or DIPAM, and that its DPR was expected to go to NALCO's board within about two months. Management's stated rationale is that Neyveli Lignite Corporation has coal mines near the proposed plant and would supply coal at production cost without a premium.
What could change NALCO's expansion schedule?
NALCO's fifth-stream timetable depends on completing the three or four critical-path packages that were 90% to 92% complete on November 3, 2026. A January 2027 production start would still be followed by a three-to-five-month commissioning ramp-up, so output during the first months would not equal the stream's 1 million-tonne rated capacity.
Raw-material developments also remain relevant to the refinery plan. NALCO said Pottangi mine development faced resistance to tree clearing for the road from the national highway to the mine. Management said the Ministry of Mines and state government were addressing the issue and hoped for resolution within two to three months.
NALCO is targeting 4.8 million tonnes of Utkal coal production in FY27, compared with 4 million tonnes in the previous year, according to management. It said clearances were in place but the environmental clearance process for 4.8 million tonnes was still under way, with an expected decision within two or three months. For Angul, the unresolved milestones remain DPR approval, land availability, package orders and execution of the linked power plant.
Conclusion
NALCO has set out a sequential expansion timetable: a fifth refinery stream targeted to begin production in late December 2026 or early January 2027, followed by the Angul brownfield smelter expansion targeted for commissioning in the first quarter of FY31. The refinery can add alumina in FY27 but requires up to five months to reach rated capacity, while Angul is a larger Rs 17,000-18,000 crore project supported by a proposed coal-linked power venture.
The next disclosed milestones are completion of the Angul DPR in January or February 2027, potential board approval in February 2027, expected land availability in February or March 2027 and package ordering by December 2027. NALCO's progress on critical refinery packages, the Pottangi road-clearing matter, Utkal's environmental clearance and the power joint venture's DPR will indicate whether management can maintain the stated schedule.