NALCO targets 2030-31 commissioning for Rs 30,000 crore
Key highlights
- NALCO targets 2030-31 commissioning for a Rs 30,000 crore Anugola smelter expansion.
- The Anugola project would add 0.5 MTPA, lifting capacity from 0.46 MTPA to about 1.0 MTPA.
- NALCO and NLC India Limited plan a 50:50 joint venture for a 4 × 270 MW captive thermal plant.
- NALCO envisages 200 MW to 250 MW of renewable energy within the Anugola project ecosystem.
powered by IRIS

National Aluminium Company Limited (NALCO) is targeting commissioning during 2030-31 for its Rs 30,000 crore Anugola smelter expansion, designed to add 0.5 million tonnes per annum (MTPA) and raise capacity from 0.46 MTPA to about 1.0 MTPA. The 4 November 2026 announcement also disclosed land-acquisition discussions, technology licensing and a captive-power joint-venture plan.
Know National Aluminium Company inside out
Results, valuation, peers and who's buying, in one view.
What capacity will NALCO's Anugola expansion add?
NALCO plans to add 0.5 MTPA of aluminium smelting capacity at its brownfield Anugola project in Odisha. The addition would increase the existing Anugola smelting capacity of 0.46 MTPA to approximately 1.0 MTPA, which NALCO described as nearly doubling capacity. The project has an approved investment of approximately Rs 30,000 crore and is targeted for commissioning during 2030-31.
The proposed increase is material because the new 0.5 MTPA stream is larger than the 0.46 MTPA existing base. NALCO's disclosed post-expansion capacity is approximate, so the stated 1.0 MTPA is the company’s planned level rather than a separately reported operating result. The announcement identifies the project as a brownfield expansion at Anugola.
Which project-enabling steps has NALCO disclosed?
NALCO disclosed that a meeting of the Rehabilitation and Peripheral Development Advisory Committee (RPDAC) was recently held to facilitate acquisition of land required for the Anugola expansion. The meeting was intended to expedite land acquisition, compensation and rehabilitation issues, placing these matters among the enabling steps identified in the 4 November 2026 release.
The announcement does not state that land acquisition has been completed, nor does it quantify the required land area, compensation or rehabilitation spending. It instead reports an RPDAC process aimed at addressing those requirements. This distinction matters because the project’s commissioning target is during 2030-31, while the disclosed land work remains framed around facilitating acquisition and speeding related issues.
NALCO also said the Anugola expansion is being pursued with support from the Government of Odisha and the Ministry of Mines, Government of India. The company linked the 0.5 MTPA project, along with the 5th Stream Alumina Refinery Project at Damanjodi, to expected additions in production capacity, employment and regional economic activity. No employment number or project-level economic-growth estimate was provided in the release.
Got a follow-up? Ask IRIS
How will NALCO power the larger Anugola smelter?
NALCO said the 0.5 MTPA Anugola expansion will require an additional 1,100 megawatts (MW) of power. To meet that need, it has partnered with NLC India Limited to establish a 50:50 joint venture company for a 4 × 270 MW, or 1,080 MW, captive thermal power plant. The joint-venture structure gives each partner an equal ownership stake in the proposed power vehicle.
The 1,080 MW thermal plant specified for the joint venture is 20 MW below the additional 1,100 MW power requirement stated for the smelter expansion. NALCO also envisages integrating 200 MW to 250 MW of renewable energy into the project ecosystem. The release does not specify the renewable technology, development timetable, ownership structure or how generation from these resources would be allocated.
NALCO has also entered an agreement with Emirates Global Aluminium (EGA) to license EGA’s proprietary smelting technology for the Anugola plant. NALCO said the arrangement is intended to support adoption of globally proven and energy-efficient aluminium production processes. The announcement does not disclose the licence fee, technology implementation schedule, operating-performance guarantees or expected unit-power consumption.
What is NALCO's plan for alumina and further aluminium projects?
NALCO said commissioning of the ongoing 5th Stream Refinery at Damanjodi is expected to generate surplus alumina even after meeting the requirements of the expanded Anugola smelter. The company plans initially to direct that surplus alumina to export markets. This establishes a link between the refinery project and the planned 0.5 MTPA Anugola expansion, although the release does not disclose the refinery’s commissioning date or surplus-alumina volume.
Beyond the Anugola project, NALCO is exploring suitable locations across India for greenfield aluminium projects as part of its long-term growth strategy. It is also evaluating a new 0.5 MTPA greenfield aluminium smelter in the country, intended to convert surplus alumina into finished aluminium. The company has not identified a location, capital cost, power source, partner or commissioning target for that separate 0.5 MTPA proposal.
The two 0.5 MTPA smelter initiatives are at different stages and should not be combined as a single committed capacity addition. The Anugola brownfield project carries an approved investment of approximately Rs 30,000 crore and a 2030-31 commissioning target. The additional greenfield smelter is described as under evaluation, while the immediate planned destination for surplus alumina is export markets.
Conclusion
NALCO’s 4 November 2026 disclosure shows that its Anugola expansion has progressed beyond a capacity proposal through RPDAC land discussions, an EGA technology-licensing agreement and a 50:50 power joint venture with NLC India Limited. If commissioned in 2030-31 as targeted, the Rs 30,000 crore project would add 0.5 MTPA to the 0.46 MTPA existing smelter and take capacity to approximately 1.0 MTPA.
The next points to watch are progress on land acquisition, compensation and rehabilitation, formation and execution of the 4 × 270 MW captive thermal-power plan, and the envisaged 200 MW to 250 MW renewable-energy integration. NALCO’s commissioning of the 5th Stream Refinery and its evaluation of a separate 0.5 MTPA greenfield smelter will also determine how surplus alumina is allocated between exports and domestic value addition.