Ravindra Energy targets 500 MW operating by March 2027
Key highlights
- Ravindra Energy reported 261.21 MW of operating renewable capacity and 231.10 MW under construction on November 5, 2026.
- Ravindra Energy targets a 500 MW operating renewable portfolio by March 2027.
- Ravindra Energy expects about 300 MW of operating capacity in Q3 FY27 and about 400 MW in Q4 FY27.
- Ravindra Energy's renewable-business EBITDA rose to Rs 93.7 crore in H1 FY27 from Rs 67.3 crore in H1 FY26.
powered by IRIS

On November 5, 2026, Ravindra Energy Limited said it was targeting a 500 MW operating renewable portfolio by March 2027, supported by 261.21 MW in operation and 231.10 MW under construction, with management saying land was acquired and power purchase agreements were signed in most construction cases.
Know Ravindra Energy inside out
Results, valuation, peers and who's buying, in one view.
Can Ravindra Energy reach 500 MW of operating capacity by March 2027?
Ravindra Energy said it is on track to reach 500 MW of operating renewable capacity by March 2027. The company disclosed 261.21 MW of operating capacity and 231.10 MW under construction during its Q2 and H1 FY27 earnings call, which covered the quarter and half year ended September 30, 2026.
The disclosed operating and construction portfolios add to 492.31 MW, or 7.69 MW below the stated target. Management did not identify a separate project for that difference, and it described the 500 MW objective as a target. The company’s stated basis for the construction pipeline is that land has already been acquired and power purchase agreements, or PPAs, have been signed in most cases.
When does Ravindra Energy expect new capacity to begin operating?
Ravindra Energy expects operating capacity of about 300 MW in Q3 FY27 and about 400 MW in Q4 FY27, according to management. Those indications compare with the 261.21 MW operating portfolio disclosed on November 5, 2026, and point to commissioning activity during the second half of FY27.
Management also said Ravindra Energy had close to 100 MW of capacity in the previous year and expects 200 MW to 220 MW of capacity addition in the current year. The call did not provide asset-level commissioning dates or explain how the about-400-MW Q4 FY27 indication will progress to the 500-MW March 2027 objective.
Ravindra Energy reported generation of about 66 million units in Q2 FY27 and 145 million units in H1 FY27. The company did not provide comparable generation for H1 FY26, generation by project, or plant-utilisation data, so the call does not quantify output changes from the operating portfolio over the prior year.
What is in place for Ravindra Energy's construction portfolio?
Ravindra Energy said land was acquired and PPAs were signed in most cases across the 231.10 MW under-construction portfolio. A PPA governs electricity sales, so management identified land control and contracted offtake as completed steps supporting the projects being built.
The qualification “most cases” means the statement did not cover every project in the 231.10 MW pipeline. Ravindra Energy did not disclose project locations, customers, tariffs, capital expenditure, financing, remaining approvals or individual completion dates during the November 5 call.
Ravindra Energy said its renewable business includes independent power production, engineering, procurement and construction, or EPC, electricity generation and trading. That mix matters because the reported revenue base includes activities beyond generation from the 261.21 MW operating portfolio.
Got a follow-up? Ask IRIS
How did Ravindra Energy's renewable business perform in H1 FY27?
Ravindra Energy reported H1 FY27 revenue of Rs 310 crore, compared with Rs 287 crore in H1 FY26, while renewable-business EBITDA was Rs 93.7 crore versus Rs 67.3 crore. EBITDA means earnings before interest, tax, depreciation and amortisation, and the figures show that EBITDA rose by Rs 26.4 crore as revenue increased by Rs 23 crore.
In Q2 FY27, Ravindra Energy reported Rs 31 crore of electricity-generation revenue, Rs 26 crore of electricity-trading revenue and Rs 133 crore from EPC and service-concession equipment. These components total the company’s reported quarterly revenue of Rs 190 crore, with EPC and service-concession equipment the largest disclosed revenue stream.
Why did Ravindra Energy's profit trail its EBITDA growth?
Ravindra Energy said H1 FY27 profit after tax before Energy in Motion losses was Rs 38.1 crore, compared with Rs 47.4 crore a year earlier, because of a lower EPC and CA revenue book in the comparative Q1 period. This occurred even as H1 renewable-business EBITDA rose to Rs 93.7 crore from Rs 67.3 crore.
On a consolidated basis, Ravindra Energy reported H1 FY27 profit after tax of Rs 20.7 crore, versus Rs 46.6 crore in H1 FY26, after losses at Energy in Motion. Q2 consolidated profit after tax was Rs 19 crore versus Rs 24.4 crore, while profit before Energy in Motion losses was Rs 26 crore versus Rs 24.4 crore.
Energy in Motion reported quarterly sales of Rs 130.8 crore, compared with Rs 44 crore in the preceding quarter, and network sales of Rs 10.7 crore versus Rs 6.5 crore. Management said that business targets turning positive in the next financial year, while continuing investment in charging-network and after-sales expansion.
Conclusion
Ravindra Energy has disclosed a defined capacity route to its March 2027 target, with 261.21 MW operating and 231.10 MW under construction as of the November 5, 2026 call. The identified capacity totals 492.31 MW, while H1 FY27 renewable-business EBITDA increased to Rs 93.7 crore from Rs 67.3 crore despite lower consolidated profit after Energy in Motion losses.
The next disclosed milestones are operating capacity of about 300 MW in Q3 FY27 and about 400 MW in Q4 FY27, alongside management’s expectation of 200 MW to 220 MW of capacity addition for the full year. Updates on commissioning, the remaining gap to 500 MW, and Energy in Motion’s target to turn positive in the next financial year will determine how the group’s reported financial mix develops.