Hindustan Zinc Limited approves Rs 80,000 crore capacity plan
Key highlights
- Hindustan Zinc Limited approved around Rs 80,000 crore for an integrated brownfield expansion programme.
- HZL targets refined metal capacity of 2 million tonnes per annum, up from 1.1 million tonnes per annum.
- HZL plans to increase silver refining capacity from 800 tonnes to 1,500 tonnes per annum.
- HZL plans to increase mine operations from 18 million tonnes to 35 million tonnes.
powered by IRIS

Hindustan Zinc Limited approved a Rs 80,000 crore brownfield expansion on November 16, 2026, targeting integrated refined metal capacity of 2 million tonnes per annum from 1.1 million tonnes per annum within three to five years. The plan also seeks to raise silver refining capacity from 800 tonnes to 1,500 tonnes per annum.
Know Hindustan Zinc inside out
Results, valuation, peers and who's buying, in one view.
What has HZL approved under the capacity plan?
HZL has approved projects to take integrated refined metal capacity to 2 million tonnes per annum and silver refining capacity to 1,500 tonnes per annum. Management announced the Board approval in the November 16, 2026 investor conference call and said the programme will be a brownfield expansion across existing asset locations under its HZL 2.0 programme.
The Rs 80,000 crore outlay covers the complete integrated plan, including the previously approved integrated zinc smelter at Debari. Management said the expansion will be supported by corresponding mining and concentration functions, connecting the proposed smelting additions with a larger upstream ore-processing system.
The plan includes a 765 thousand tonnes per annum, or KTPA, zinc smelter, a 200 KTPA lead smelter and 700 tonnes per annum of additional silver refining capacity. After completion, HZL expects integrated zinc capacity of 1.6 million tonnes per annum, integrated lead capacity of 0.4 million tonnes per annum and silver refining capacity of 1,500 tonnes per annum.
How much will HZL spend and when could commissioning occur?
HZL expects to phase the Rs 80,000 crore capital expenditure over almost five years, while management gave an expected commissioning window of three to five years. It said about 60% of capital expenditure is generally incurred during construction, with the remaining spending extending into the next two years.
The Rs 80,000 crore total includes Rs 14,000 crore of earlier approvals, comprising Rs 12,000 crore for the original project and Rs 2,000 crore for exploration and other facilities. The latest Board decision therefore adds about Rs 65,000 crore to Rs 66,000 crore, based on management's conceptual design for the full project.
Management said about Rs 30,000 crore of the additional approval will broadly be used to expand mining operations. The mining plan has increased from 18 million tonnes to 35 million tonnes and includes two shafts that were not anticipated in the initial plan, alongside power, water, land and other project requirements.
How will HZL's mining and smelting system change?
HZL plans to increase mine operations to 35 million tonnes from 18 million tonnes as part of the integrated expansion. The original first-phase approval focused only on a zinc smelter and did not include lead and silver capacity, according to management, whereas the revised design incorporates larger mining operations, two shafts, lead smelting and additional silver refining.
The earlier mining plan could meet an additional 250 KTPA requirement using available space, management said. Moving to the larger 35-million-tonne mine plan requires broader mine development, which management cited as a reason the total programme cost increased from the earlier Rs 14,000 crore approval base to Rs 80,000 crore.
The 765 KTPA zinc-smelter addition, 200 KTPA lead smelter and 700-tonne-per-annum silver-refining addition are intended to support the new end-state capacity mix. The refined-metal target of 2 million tonnes per annum is about 82% above the current 1.1 million tonnes per annum, while the silver target of 1,500 tonnes per annum is 87.5% above current 800 tonnes per annum capacity.
Got a follow-up? Ask IRIS
How does HZL intend to fund the Rs 80,000 crore project?
HZL said it has flexibility to fund the Rs 80,000 crore programme through debt, internal accruals or a combination of both. Management said it will assess interest rates and free cash flow available when deciding the financing mix, but did not disclose a debt amount, annual funding plan or final split between the two sources.
Management's stated operating objective is to keep zinc production cost, excluding royalty, below $1,000 per tonne after the expansion. It attributed that target to operational efficiency, economies of scale, digitalisation and automation, and it remains a management target rather than a reported post-expansion cost outcome.
The chief financial officer said conservative conceptual-design assumptions indicate a return in the under-mid-teen range for the project. Management expressed hope of achieving more, but did not provide a detailed internal rate of return, metal-price assumption, commissioning sequence or segment-wise capital expenditure allocation during the November 16 call.
What approvals and lease matters does HZL still face?
HZL requires environmental clearance, Consent to Establish, or CTE, and Consent to Operate, or CTO, for the projects. Management said some approval processes had started while the projects were being conceptually planned, while the mining-capacity increase also needs fresh mine plans and environmental clearance.
HZL has land at existing locations for the main facilities, management said, but is acquiring land privately for certain auxiliary requirements. The use of existing sites supports the brownfield approach, although the plan still includes land-acquisition activity for supporting infrastructure.
Management said 35% of its mining assets will continue beyond 2030, leaving about 65% subject to lease renewals in 2030. HZL said it has a legal first right of refusal for those mines and expressed confidence in operational continuity, while noting that the government is formulating measures to address abnormal bidding in mine auctions.
Conclusion
HZL's Rs 80,000 crore approval combines a mine expansion from 18 million tonnes to 35 million tonnes with new zinc and lead smelting and higher silver refining. The plan would lift integrated refined metal capacity from 1.1 million tonnes to 2 million tonnes per annum and silver refining capacity from 800 tonnes to 1,500 tonnes per annum, subject to execution of linked upstream and downstream projects.
The next developments to watch are the three-to-five-year commissioning timetable, progress on environmental, CTE and CTO approvals, and the choice between debt and internal accruals for funding. HZL also needs to progress fresh mine plans, auxiliary land acquisition and the 2030 lease-renewal process affecting about 65% of its mining assets.